Unlike a typical commercial site, The Depot property did not provide the usual laydown or staging area for materials. Considerations were made for this constraint early on, and it was decided that the use of the ConXtech system for the building’s structural steel would make the most sense as a smart work-around. The offsite fabrication with ConXtech created a world of difference in the overall timing and schedule of The Depot.
“The install was very fast and accurate. We were able to erect the entire three-story building in about two weeks,” said KPRS Project Manager Zareh K, who led the project onsite. “All the materials were fabricated off site at ConXtech certified shops, which cut down on site labor costs as well as inspection times.”
For this smooth and quick install, the coordination needed beforehand was key, particularly during the preconstruction phase. Since the whole system is ready to go once it arrives at the site, with specific bolted connections already established with the ConXteam, only small portions can be modified.
“While there’s more flexibility with a traditional structural install, if you have the right coordination ahead of time then this is a fantastic system for a variety of projects, and especially met our needs for The Depot,” said Matt Muns, KPRS Vice President of Construction.